Yamazumi Chart & Line Balancing Tool

Build a stacked workload chart, move tasks between stations and compare time above takt with a baseline. Free manual line balancing, with no signup.

No signup · Calculated in your browserInput data and results are not stored or sent to servers, analytics or external APIs. Inputs are lost when you leave, reload or switch language.

Move tasks and compare station workloads

Stations

Tasks

Takt 50 sLoad part: 25 sPosition part: 15 s40Station 1Process part: 50 sVisual inspection: 15 s65Station 2Measurement: 20 sUnload part: 15 s35Station 3
Each colored segment is a task. The dashed line marks target takt time.
Total work time
140 s
Total time above takt
15 s
Longest station
Station 2 65 s

Compare with baseline

Total time above takt 15 s → 15 s / Total work time 140 s → 140 s

Build and compare a workload chart

Enter target takt time in seconds. Add stations and tasks, enter each task duration, and select its assigned station. Each colored segment in the chart represents one task. The sample is fictional.

Use Set current state as baseline before changing assignments. Moving a task redistributes time without changing total work time. Deleting a station moves its tasks to the first remaining station; at least one station is retained. Reset sample restores both the working state and baseline.

Takt time and time above takt

Takt time is available production time divided by customer demand, expressed in consistent units. This tool accepts your target takt rather than calculating demand.

The chart follows the yamazumi approach of stacking work elements against takt. Here, each bar represents a station. Total time above takt is the sum of each station's positive excess over the target. It is not a direct prediction of output or elapsed line cycle time.

Check whether a reassignment is feasible

The tool supports manual comparison, not automatic optimization. It does not validate task precedence, travel, parallel work, machine capacity, safety or operator qualifications. Check those constraints before applying a proposed assignment.